Review of the Florida Department of Transportation Construction Bid and Contract Administration Process, Report No. 96-85, May 1997
 
Full report in PDF format


  • Successful bids in the projects we examined averaged 6% below the Florida Department of Transportation's (FDOT) official preliminary estimates. Final construction costs averaged 9% above the award amounts, resulting in $32┬ámillion in cost overruns.
  • FDOT paid about $2 million above average bid prices for increased quantities of planned work. FDOT could avoid paying these premium prices by adopting a policy to pay only reasonable unit prices when quantity overruns occur.
  • FDOT advance payment practices for certain items resulted in $90,000 in potential lost interest earnings to the state. FDOT could avoid the loss of potential interest earnings by retaining a portion of the payment for certain contract items.

Which Government Program Summaries contain related information?

Planning and Environment
Pre-Construction and Design Services
Florida Commission for the Transportation Disadvantaged

What other OPPAGA-related materials are available?

  • Report No. 99-29 Justification Review of the Highway Construction and Engineering and Transportation System Maintenance Programs, published in January 2000
  • Report No. 99-24 Justification Review of the Public Transportation Program, published in January 2000
  • Report No. 98-86 Justification Review of the Motor Carrier Compliance Program, published in June 1999
  • Report No. 98-60 Florida Department of Transportation's Programs' Performance for Fiscal Year 1997-98, published in February 1999
  • Report No. 98-59 Transportation System Maintenance Program, published in February 1999
  • Report No. 98-58 Highway Construction and Engineering Program, published in February 1999
  • Report No. 98-57 Toll Operations Program, published in February 1999
  • Report No. 98-56 Right-of-Way Acquisition Program, published in February 1999
  • Report No. 98-55 Public Transportation Program, published in February 1999
  • Report No. 98-54 Motor Carrier Compliance Program, published in February 1999
  • Report No. 97-22 Follow-up Report on the Florida Department of Transportation's Performance In Controlling Cost Overruns When Building Roads and Bridges (December 1997)
  • Report No. 96-21 Review of the Florida Department of Transportation's Performance in Controlling Construction Cost Overruns and Establishing Accountability for These Problems (November 1996); and
  • Report No. 95-30 Florida Department of Transportation's Performance in Controlling Cost Overruns and Delays When Building Roads and Bridges (January 1996)

Copies of this report in print or alternate accessible format may be obtained by telephone (850/488-0021), by FAX (850/487-9213), in person, or by mail (OPPAGA Report Production, Claude Pepper Building, Room 312, 111 W. Madison St., Tallahassee, FL 32399-1475).
e-mail address: oppaga@oppaga.fl.gov


Reports  |  Home